Airstrip 2020- “Subproject of Reconstruction of connecting roads to Runway B, W and W2”
Location: Tirane
Surface: 1.6km
Client: Tirana International Airport (Mother Teresa)
Current Status: Finished
Year: 2019-2020
Supervisor: “INFRAKONSULT” SH.P. K & AL MUHANDIS
During the implementation phase, the implementation for the construction of new taxiways with a length of 1.6km, the cross section of which has a width of 44m, with 11.5m lanes each and 10.5m wide double-sided embankments has been meticulously followed. The drainage of surface waters of the taxiway, the electrical project and the taxiway signage have also been carried out.