“Study and Design of Infrastructure Facilities for Irrigation, Drainage and Flood Protection for the Year 2015-2016, SHKODER”

The irrigation canal rehabilitation project includes three areas:

  • Hajmel irrigation canals

The length of the main and secondary canals is about 20km. The rehabilitation consists of the rehabilitation of the canals on the designed route (cleaning works, repair of existing damaged works, damaged concrete linings), new concrete linings, changing the route depending on the current situation where the scheme is located, construction of new works where necessary.

 

  • Irrigation Scheme Over Shkodra

The length of the main and secondary canals is 240km. Most of the main canal network has been designed in recent years and cleaning and maintenance works are carried out on them. The rehabilitation has included the final part of the main Grizhë - Koplik canal with a length of 9km and the rehabilitation of 140km of the secondary canal network on the designed route (cleaning works, repair of existing damaged works, damaged concrete linings), new concrete linings, changing the route depending on the current situation where the scheme is located, construction of new works where necessary.

  • Juban Gur Zi Irrigation Scheme

The length of the main and secondary canals is 45km. The rehabilitation will consist of the rehabilitation of the canals on the designed route (cleaning works, repair of existing damaged works, damaged concrete linings), new concrete linings, changing the route depending on the current situation where the scheme is located, construction of new works where necessary.
Also part of the contract are the construction of two embankments in Darragjat and Kir. The river protection in Darragjat has a length of 112m of longitudinal protection, and along a length of about 1425m, 12 gabion brushes have been built. The axis of the embankment in Kir has a length of about 1560m. The body of the embankment will be filled with gravel, the surface coating will be with gabions and Geoweb cells.

Location: Shkoder
Length: 305 km
Client: Shkoder Municipality

Current Status: Finished
Year: 2015
Designers:  InfraKonsult